Earned Value Made Simple: CPI, SPI and Estimate at Completion

Earned value calculator

Earned value answers two questions with three numbers: are we spending more than the work we have done is worth, and are we behind the plan?

The three numbers

  • Planned value (PV): the budget of the work that should be done by today.
  • Earned value (EV): the budget of the work that is actually done.
  • Actual cost (AC): what has really been spent.

Example

A project with a $120,000 budget should be 50% done (PV $60,000) but is 42% done (EV $50,400), and has cost $58,000.

The indexes

Cost performance (CPI) is EV divided by AC: 0.87. Each dollar spent buys 87 cents of planned work. Schedule performance (SPI) is EV divided by PV: 0.84, so the project is behind schedule.

Where it will finish

If cost performance stays the same, the estimate at completion is the budget divided by CPI: about $138,095, or $18,095 over budget. Catching this at 42% leaves time to change scope, staffing or plan.

Do it in one minute

Our free earned value calculator shows CPI, SPI and the estimate at completion. No sign-up, nothing stored.

To see late tasks, overbooked people, budget overruns and risks weeks early, see the Project Management System. Black Friday: code BF50 takes 50% off at checkout until December 1.