Most bad development deals were bad on the day the land was bought. A one-page feasibility before you commit shows whether there is enough profit to survive the surprises every project brings.
Step 1: total development cost
Take a small project of 8 units on land costing $400,000:
- Build cost: 8 units at $180,000 is $1,440,000
- Soft costs (design, permits, fees) at 12% of build: $172,800
- Finance at 6% of land and build: $110,400
- Selling costs at 3% of sales: $79,200
Total development cost: $2,202,400.
Step 2: sales and profit
8 units at $330,000 sell for $2,640,000, which leaves $437,600 of profit.
Step 3: the two ratios
Profit on cost is profit divided by total cost: 19.87%. Margin on sales is profit divided by sales: 16.58%. Lenders and partners often look at both, and many want a cushion before they commit.
Stress test it
If sale prices fall 5%, profit drops by about $128,000, to roughly 14% on cost. If a project only works at today's best prices, it does not really work.
Do it in one minute
Our free property development feasibility calculator shows total cost, profit and profit on cost as you change any input. No sign-up, nothing stored.