Earned value answers two questions with three numbers: are we spending more than the work we have done is worth, and are we behind the plan?
The three numbers
- Planned value (PV): the budget of the work that should be done by today.
- Earned value (EV): the budget of the work that is actually done.
- Actual cost (AC): what has really been spent.
Example
A project with a $120,000 budget should be 50% done (PV $60,000) but is 42% done (EV $50,400), and has cost $58,000.
The indexes
Cost performance (CPI) is EV divided by AC: 0.87. Each dollar spent buys 87 cents of planned work. Schedule performance (SPI) is EV divided by PV: 0.84, so the project is behind schedule.
Where it will finish
If cost performance stays the same, the estimate at completion is the budget divided by CPI: about $138,095, or $18,095 over budget. Catching this at 42% leaves time to change scope, staffing or plan.
Do it in one minute
Our free earned value calculator shows CPI, SPI and the estimate at completion. No sign-up, nothing stored.